Posted August 16, 2011 by Karen Nelson
Construction of the new Briarwood is happening on schedule and we're all watching the progress. You can check out the changes -in this aerial slide show. Here's the latest:
- Framing is complete; all but stage, commons and gym and will be 100% by April
- Steel exterior stairs and bridge will be delivered by April.
- Off site sewer work is underway and expected to be completed by April.
- Site concrete will commence mid April.
- Electrical and mechanical work is being roughed in the Administration offices and completed in the classrooms.
- The main two story building is dried-in; windows, metal roofing, metal siding, and block veneer are nearing completion.
- Exterior and interior doors and hardware are arriving early April.
- Wall covering is completed in all classrooms, millwork is nearly complete in north wing classrooms, and ceiling grid is being installed in all classrooms.
- Concrete stone work is complete in the library and electrical rough in is underway.
- Project is on schedule for substantial completion.
Sketches of the new school are available on the Issaquah district website. The plans are also on display in the school office.