Construction of the new Briarwood is happening on schedule and we're all watching the progress. You can check out the changes -in this aerial slide show.  Here's the latest:

 

  • Framing is complete; all but stage, commons and gym and will be 100% by April
  • Steel exterior stairs and bridge will be delivered by April.
  • Off site sewer work is underway and expected to be completed by April.
  • Site concrete will commence mid April.
  • Electrical and mechanical work is being roughed in the Administration offices and completed in the classrooms.
  • The main two story building is dried-in; windows, metal roofing, metal siding, and block veneer are nearing completion.
  • Exterior and interior doors and hardware are arriving early April.
  • Wall covering is completed in all classrooms, millwork is nearly complete in north wing classrooms, and ceiling grid is being installed in all classrooms.
  • Concrete stone work is complete in the library and electrical rough in is underway.
  • Project is on schedule for substantial completion.

 Sketches of the new school are available on the Issaquah district website. The plans are also on display in the school office.